WE’VE DONE IT!
Montemor-o-Novo’s castle info kiosk is waiting for your visit!

11150329_813377195407609_7046031208641529617_n


LATEST EVENTS:

kiki


Alma de Arame play “Troll Times” uses the kiosk as a foyer and ticket office:

alma de arame2 


HOW DID WE ARRIVE HERE:

Week #1 and  #2
from 22.09.2014 till 03.10.2014
Manufacturing the Compressed Earth Stabilized Bricks (CESB) with a team of volunteers

S0470675

Week #3
from 06.10.2014 till 11.10.2014
Theoretical classes and idea competition for the site represented in models.
Forming 6 groups, each one proposing a project for the site.
Presentation of the ideas to the community and pre selection.

castles hill topographyDSCF1299

Groups presentation each project to the workshop leaders

Week #4
from 13.10.2014 till 18.10.2014
Choosing the most suitable project and gather all the participants to concentrate forces on developing the selected one.
Starting the foundation.
First saturday of talks/presentations (see more program details on the section Events-Talks).

DSCF0968

Week #5
from 20.10.2014 till 26.10.2014
Finishing the foundations and preparing the formwork.
Starting the walls.

Arch Formwork

Week #6
from 28.10.2014 till 01.11.2014
Two arches. One vault. Two benches. Walls. Ground. Landscape ground shaping.

Buiding without plaster

Winter time come up…
Slowly slowly the Montemor team is finishing the roof and the pavement preparing for the winter.

1rst phase finished building

Take#2 week #1 . The CSEB production
from 16.03.2015 till 21.03.2015
4 volunteers . 850 CSEB . some colorful experiences . a visit to the Escoural caves . fun!

Watch the video here.

10898199_887308904666354_8346448442570248162_n

Take#2 week #2 . Making tiles and details
from 13.03.2015 till 28.03.2015
4 volunteers . 6 60×40 light tiles to be laser engraved . dozens of floor glazed dots . hundreds of tiles joints . fun! [and there was still time for learning a bit of typography for some]

11082575_807839405961388_262448230457841719_n

Take#2 week #3 . Building the last arch and finishings
from 30.03.2015 till 04.04.2015
After an intense week of practice and theory on CSEB and arches, the final structure is 98% finished. There is only the tiles to laser engrave!

10436038_813376502074345_1239101066739465833_n